Hi Friends,
I have a Scenario here wherein one of my openhub is loaded data via DSO through Delta DTP daily.
The openhub Destination is a flatfile in this case.
This openhub creates one csv file and 2 XML files daily.
Eg: on 3rd feb as per the downsteams ,he received only 2 XML files and no csv file. We have no logs in our system to verify these too.
There was no Abort in process chain on that day.
so now now we have to reload the data for 4th feb again.
1) One Option is to delete all the openhub requests from 4thfeb till date and do a reload from dso to openhub for all the requests from 3rd feb to current date .
2) Another possibility would have been to put some filter for date field or request id field in DTP and reload data particularly only for 3rd feb.
But in our case we dont have any useful filters in DTP to do so.
3) Do we have another Options to reload the data particularly for 3rdfeb.
Kindly respond. Thanks.
Regards,
Jini